Crows Nest Substation

The works involved at Crows Nest Substation included the demolition of an existing office building and the construction of a basement which included oil tanks, flame traps and cable pits as well as a ground floor level with GIS room and two transformer bays. The substation improved its architectural aesthetics by installing a concrete precast panel wall façade system, louvers and metal roofing.

Level 1, 9-13 Underwood Avenue,
Botany NSW 2019

PO Box 659 Botany
NSW 1455 Australia

Phone: + 61 2 9289 3700
Fax: + 61 2 9289 3730